Last updated October 29, 2026
Short answer: Both towns rebuild their beaches with sand, but in very different ways. Surf City has signed on to a 50-year U.S. Army Corps of Engineers project that will rebuild about 6 miles of its beach, with bids expected in fall 2027 and construction expected to start in early 2028. North Topsail Beach left that federal partnership in 2021 and now runs its own phase-by-phase program paid for with FEMA money, state grants and local beach funds. At the island’s north tip, the town’s preferred long-term plan includes a 2,021-foot terminal groin at New River Inlet. That plan is still in environmental review. Nothing has been permitted, funded or built.
If you’ve walked the beach here in winter and wondered about the dump trucks, the long black pipe or the freshly rebuilt dunes, this guide is for you. We live and work on this island, and we care about these beaches. Here is what’s happening, where the money comes from, and what it means for your next stay.
Where each project stands
| Project | Key dates | Status as of October 29, 2026 |
|---|---|---|
| Surf City federal project | Authorized 2014; Chief’s Report signed July 15, 2025; partnership agreement signed August 17, 2026 | Construction money approved June 30, 2026. Bids expected fall 2027, first build expected to start early 2028 and take about 16 months. Future renourishments passed the House on September 16, 2026; the Senate has not voted. |
| North Topsail Beach phases 1 to 5 | Phase 5 truck haul 2022 to May 2024; Phase 4 truck haul winter 2024 to 2025; Phases 1 to 3 emergency dune January to February 2026 | Town-run program, project by project, paid for with FEMA money, state grants and local beach funds. Not part of the federal project. |
| New River Inlet terminal groin | Draft EIS released September 4, 2026; comments closed October 19, 2026; final EIS expected around March 2027 | Proposed only. Not permitted, funded or built. A Corps decision could come in summer 2027. |
What this means for your Topsail vacation
- Summer stays: Sand projects in North Topsail Beach normally finish by April 30, so most summer visitors never see them. The exception to plan around is Surf City’s first federal construction, expected to start in early 2028 and run about 16 months. Details on beach closures during that work haven’t been announced yet; we’ll update this post when they are.
- Winter and spring stays: You may see dump trucks at a few marked beach accesses in North Topsail Beach, or a pipeline with bulldozers. Crews add temporary crossings over the pipe. Give equipment plenty of room, and keep kids clear of the work zone.
- The north end: The beach near New River Inlet is narrow and changes fast, and new warning signs went up in the area this summer after several drownings (WWAY). Swim near the main beach, not in the inlet.
- Help the dunes: Use the walkovers, stay off the dunes, and leave the sea oats alone. Those plants hold the sand that protects the homes and roads behind them.
Looking for a place to stay? Browse our Surf City vacation rentals and North Topsail Beach vacation rentals, or find the closest walkway to the sand on our Topsail Island public beach access map.
What beach nourishment actually is
Barrier islands are always moving. Waves and currents carry sand along the shore, storms pull it offshore, and inlets swallow it. Beach nourishment (also called renourishment) puts sand back. Crews pump sand from offshore or from a dredged channel, or truck it in from an inland mine. Then they shape it into a wider beach (the berm) and a taller, vegetated dune behind it.
Nourishment doesn’t stop erosion. It gives the ocean sand to take instead of houses, roads and dunes, which is why every project here is planned around repeat cycles.
On Topsail you’ll see three kinds of projects:
| Method | What you’ll see | Used here |
|---|---|---|
| Offshore dredge and pipeline | A large pipe running along the beach, bulldozers spreading sand, work around the clock | North Topsail Beach (2015); Surf City’s federal project |
| Channel dredging (beneficial use) | Same pipe, with sand from the Intracoastal Waterway, a navigation channel or an old disposal island | Army Corps waterway dredging placed on North Topsail’s north end; Surf City’s 2025 Banks Channel project |
| Truck haul | Dump trucks driving onto the beach at a few marked accesses, usually on weekdays | North Topsail Beach’s FEMA and state-grant phases, 2021–2026 |

Why most sand work happens in winter
Sea turtle nesting and hatching season here runs from May 1 to November 15, and shorebirds nest in spring and summer (Corps draft environmental study, 2026). To protect them, North Topsail Beach’s permits generally allow sand placement only from November 16 to April 30. When the town asked to start on November 1, 2023, the request was denied (Town of North Topsail Beach). Surf City’s future renourishments will use the same November 16 to April 30 window (USACE final report, 2025).
There is one exception worth knowing about. The Corps’ report says Surf City’s first construction “will be performed without an environmental window.” It will be a single job of about 16 months, so it will likely run through at least one summer, with turtle monitoring around the clock from May 1 (USACE; USFWS coordination appendix).
Surf City: a 50-year federal beach project
How it got here
Surf City and North Topsail Beach spent more than two decades working with the Army Corps on a joint storm-protection project. Congress authorized it in the Water Resources Reform and Development Act of 2014. It was meant to cover about 10 miles: roughly 6 in Surf City and 4 in southern North Topsail Beach (Port City Daily, 2021).
In July 2021, North Topsail Beach told the Corps it would not sign a partnership agreement because its share of the cost had climbed (Coastal Review). Surf City kept going alone, and in August 2022 the Corps approved continuing with a Surf City-only project (Port City Daily).
The milestones since
- July 15, 2025: The Chief of Engineers signed the project’s Chief’s Report, the Corps’ formal recommendation to Congress (Chief’s Report).
- June 30, 2026: Federal approval came through to use more than $292 million in previously appropriated Disaster Relief Act of 2019 money to build the project. That figure lines up with the federal share of the whole 50-year project in the Chief’s Report: about $121.8 million for the first build plus about $171.0 million for the seven renourishments, or $292.8 million. The announcements didn’t break the approval down further (Coastal Review, August 2026; WECT; Coastal Review).
- August 17, 2026: Surf City and the Army Corps signed the project partnership agreement at a ceremony at the Surf City Ocean Pier, where Mayor Teresa Batts, Wilmington District commander Lt. Col. Kenneth Porter and Rep. David Rouzer spoke (WECT; WWAY).
- September 16, 2026: The U.S. House passed the Water Resources Development Act of 2026 (H.R. 9497) by a vote of 415 to 9. The bill authorizes the project’s future renourishments at an estimated $362.3 million in total cost, of which about $171.0 million is the federal share and about $191.3 million is paid by the town and state (bill text). It also formally deauthorizes the old North Topsail Beach portion. The Senate’s version (S. 4949) cleared committee in July 2026 but has not had a full Senate vote, so it is not law (Congress.gov; Congress.gov, S. 4949; Coastal Review; NACo; Rep. Rouzer).
What the project will build
From the Chief’s Report and the Corps’ final report:
- About 6.3 miles of rebuilt dune and beach, plus a 1,000-foot transition into North Topsail Beach.
- A dune with its crest 14 feet above the vertical datum the Corps uses (NAVD 88), planted with dune grasses.
- A beach berm about 50 feet wide.
- 40 public dune walkovers.
- About 6.4 million cubic yards of sand on the beach for the first construction, dredged from offshore borrow areas 1 to 6 miles out.
- Renourishment every six years, seven times over a 50-year project life.
- Cost: $198.6 million for initial construction and $362.3 million for the seven renourishments, about $560.9 million in total at October 2024 prices. The federal government pays 61.3% of initial construction (about $121.8 million) and 47.2% of renourishments (about $171.0 million) (Chief’s Report). The town pays the rest, with support from the state.
- Benefit-cost ratio: 2.5 to 1, meaning the Corps expects about $2.50 in storm-damage savings and other benefits for every dollar spent.
Sources: Chief’s Report; final General Reevaluation Report, June 2025.
When construction starts
The Corps expects to open bids in fall 2027, start work in early 2028 and finish around spring 2029, about 16 months in all (Coastal Review, August 2026). Earlier Corps statements said “late 2027.” So far we found no bid notice, and no contractor has been hired. After the first build, the next renourishment would come about six years later.
How Surf City pays its share
Surf City has been saving for years through a beach fund that has drawn on property tax, occupancy tax and paid-parking revenue (Port City Daily, 2021). The town manager’s proposed 2026–27 budget put $4,963,415 into the Beach Nourishment Fund, paid for with accommodations tax, property tax and paid-parking revenue, and projected the fund balance would reach about $34 million in preparation for the Corps project. The council adopted the budget on June 30, 2026, with a tax rate of 47.5 cents per $100; we haven’t confirmed the final beach fund amount in the adopted ordinance (Surf City proposed budget message; WECT, July 2026).
Sand Surf City has already added
Surf City hasn’t waited on the federal project. After Hurricane Florence in 2018, the town rebuilt an emergency berm with trucked-in sand, later reimbursed in part by FEMA and the state’s Coastal Storm Damage Mitigation Fund (WECT, 2021; NC DEQ). From January to April 2025, a town-funded project dredged Banks Channel and pumped the sand onto the beach from the Topsail Beach town line to about 1,000 feet north of the Surf City pier. Crews worked around the clock in 500-foot sections (WECT; DredgeWire).
North Topsail Beach: building its beach one phase at a time
North Topsail Beach has about 11 miles of oceanfront, divided into five project “phases.” Phase 1 is the north end at New River Inlet, and Phase 5 is the south end at the Surf City line. More than half of the town’s shoreline sits inside federally designated Coastal Barrier Resources Act zones, which bar federal money for many beach projects. That’s a big reason the town relies on its own funds, FEMA storm money and state grants (DredgeWire/StarNews, 2022).

A timeline of North Topsail’s major sand projects
| When | What happened |
|---|---|
| 2012–13 | The town dredged and moved the New River Inlet channel, placing about 568,000 cubic yards of sand along 1.5 miles of the north end for about $5.6 million. The Corps’ 2026 draft environmental study says essentially all of it eroded back into the inlet within the first year (draft EIS; WWAY; town fact sheet). |
| 2014–15 | Phase 5 offshore dredge project along roughly 3.5 miles of the south end. It cost about $16.8 million, financed largely by a USDA loan (Coastal Review; USDA). |
| 2021 | FEMA-funded dune rebuilding after Hurricane Florence: about 137,500 cubic yards of sand and more than 365,000 dune plants (Rep. Murphy). |
| 2022–24 | Phase 5 FEMA truck haul for Florence and Dorian damage: about 636,000 cubic yards over three winter seasons, finished in May 2024 and covering about 3.5 miles. Town engineers later reported that this stretch held up well through Potential Tropical Cyclone Eight and Hurricane Erin (town update; Dredging Today; town coastal update, February 2026). |
| 2023 and 2025 | The Army Corps pumped sand from routine waterway dredging onto the north end, about 160,000 cubic yards in early 2023 and about 77,000 in early 2025 (town update). |
| Winter 2024–25 | Phase 4 truck haul, about 220,000 cubic yards over about 2.5 miles, funded by a $10.5 million state grant for Phases 4 and 5 and finished before turtle season (NC DEQ; town coastal update, February 2026). |
| January–February 2026 | An emergency dune and berm along about 4 miles of Phases 1–3, repairing damage from Potential Tropical Cyclone Eight, the unnamed storm of September 15 to 17, 2024 (town minutes, March 4, 2026; National Hurricane Center). |
How North Topsail pays for it
The town’s 3% share of the occupancy tax on vacation rentals goes to its Shoreline Protection Fund for beach nourishment (Town of North Topsail Beach). The beach fund also draws on property and sales taxes and most paid-parking revenue (Port City Daily, 2023). Storm repairs have been funded mostly by FEMA, with the state covering much of the remainder.
In other words, every guest who rents a home in North Topsail Beach helps pay for the sand under their beach chair.
What’s being planned next
The town’s biggest idea on the drawing board is to reuse sand from an old Army Corps disposal island near the inlet, known as DA 143, and pump its sand onto Phases 1–3. The Corps’ draft environmental study describes DA 143 as a 48-acre disposal site about 1.8 miles northwest of the north end beach, holding an estimated 1.9 million cubic yards of beach-quality sand (draft EIS). Town engineers have called it the largest nourishment in North Topsail’s history. As of fall 2026 it has no construction date, permit or funding, so treat it as a plan, not a schedule (town coastal update, February 2026; town meeting packet, April 2026).
You can also help the dunes yourself. The town runs a cost-share program for sea oats and bitter panicum plantings, with pickups at Town Hall each spring (Town of North Topsail Beach).
The terminal groin at New River Inlet
What a terminal groin is
North Carolina law defines a terminal groin as a structure built at the end of an island or the side of an inlet, running roughly perpendicular to the beach, meant to protect the island’s tip from erosion or the inlet moving. It must be pre-filled with sand and let sand flow “around, over, or through” it. The statute adds plainly: “A terminal groin is not a jetty” (G.S. 113A-115.1).
North Carolina has banned most hardened structures on its oceanfront since the 1980s. In 2011 lawmakers carved out a pilot exception for up to four terminal groins (NC DEQ report, 2024). The cap later went to six, and in 2024 to seven. Under today’s law, two of those seven permits are reserved for New River Inlet and Bogue Inlet. Any town that builds one must show proof it can pay for long-term maintenance, monitoring, mitigation and, if needed, removal (G.S. 113A-115.1).
Two have been built so far. Bald Head Island built the first in 2015–16. Ocean Isle Beach finished its groin in spring 2022 for about $11 million, after a federal appeals court rejected a challenge from the National Audubon Society (NC DEQ; Coastal Review). Figure Eight Island and Holden Beach studied groins and dropped them.
Why North Topsail’s north end wants one
The north end has fought New River Inlet for decades. The Corps’ draft environmental study traces today’s erosion to a northeastward shift in the inlet’s ebb channel that began in the early 1990s, and says the north end shoreline has receded 70 to 240 feet since 1996. By 2014, 11 first-row homes had been lost, and the state approved an unusually large sandbag wall to protect the homes still standing (Coastal Review, 2014). Today about 3,600 feet of sandbags line the northernmost beach, and the draft study counts more than 40 structures behind them as threatened. The town’s engineers say the bags held up through Hurricanes Matthew and Florence (draft EIS; Coastal Review, September 2026).

The town’s first engineering study, back in 2002, offered two options: move the inlet channel or build a terminal groin. The town chose the channel as the cheaper, faster fix (Town FAQ). The 2012–13 channel project rebuilt the north end, but essentially all of that sand washed away within the first year. Since then the town has studied a groin as a longer-term answer, with Onslow County agreeing in 2016 to split the cost of the environmental study.
The plan on the table
The plan is proposed only: it has not been permitted, funded or built. On September 4, 2026, the Army Corps’ Wilmington District released a draft environmental impact statement (EIS) for the town’s New River Inlet Master Management Plan. It weighs five options (WECT; draft EIS):
- Status quo: keep doing what’s already permitted.
- Abandon and retreat: no town-managed beach or inlet work.
- Beach nourishment only.
- Beach nourishment plus a terminal groin.
- Beach nourishment, a terminal groin and active inlet management. This is the town’s preferred option.
According to the draft EIS, the preferred option includes:
- A 2,021-foot terminal groin on the Topsail side of New River Inlet: a 345-foot steel sheet-pile anchor buried behind the dune, an 894-foot sheet-pile section across the dry beach, and a 782-foot section of 4- to 6-foot granite stones reaching into the water. The onshore sections would sit slightly below the natural beach height so people and vehicles can still cross.
- Continuing the town’s already-permitted plan to realign and maintain the inlet’s outer channel, dredged about every four years.
- A 5,100-foot dune and beach fill, with about 310,000 cubic yards of sand at the start and again about every four years.
- A cost of about $76 million over 30 years: about $18 million to build and maintain the groin and about $58 million for channel dredging and sand.
Even under the preferred plan, the draft study projects 48 oceanfront properties and 779 individually owned housing units could be at risk over 30 years, with about $275 million in property value at stake. With no town or Corps-permitted work at all, it projects 152 properties, 895 units and about $371 million. These counts come from the draft study’s own projected shoreline changes over 30 years under each option, valued at current property values (draft EIS, sections 3.1.2.1 and 3.1.5.4, citing Appendix D). They are model projections, not forecasts for any single home. For comparison, the groin-and-nourishment option without inlet channel work projects 38 properties.
What people are saying
At the September 22 public hearing at Town Hall, a standing-room crowd turned out, and most speakers backed the town’s preferred plan. “Something has to be done,” resident Terrie Hardy said (Coastal Review).
Others urged caution. Julie Youngman of the Southern Environmental Law Center didn’t take a side but said a groin “will not eliminate the need for repetitive and expensive beach nourishment and inlet dredging projects,” and asked people to “keep remembering the people downdrift” (Coastal Review). UNC-Chapel Hill coastal scientist Laura Moore told WWAY that “permanent structures aren’t a permanent solution” (WWAY). The North Carolina Coastal Federation is monitoring the project and has raised concerns about long-term costs to property owners and erosion farther down the beach (NC Coastal Federation). The study area also includes the south end of Onslow Beach across the inlet, part of Marine Corps Base Camp Lejeune.
Both sides agree on one thing: a groin wouldn’t replace nourishment. Every option on the table still includes putting sand on the beach.
What happens next
- The public comment period closed October 19, 2026.
- A final EIS is expected around March 2027, followed by a public review period of at least 30 days. The town expects to apply for permits around the same time (WECT; Coastal Review).
- A Corps decision (record of decision) could come in summer 2027, barring delays. A state permit from the Coastal Resources Commission would also be required.
- Funding is unsettled. Coastal Review calls the plan “unfunded.” State law already bars state money for terminal groins. In June 2026 the Senate Finance Committee stripped a provision from Senate Bill 1001 that would have let the state’s Coastal Storm Damage Mitigation Fund pay for them, and the bill moved on without it (Coastal Review; NCGA, S.B. 1001).
- A bigger change is pending. Senate Bill 1009 would repeal G.S. 113A-115.1 outright and end the state’s ban on hardened structures, terminal groins included. A Senate committee approved it on June 17, 2026, and it has sat in the Senate Appropriations/Base Budget committee since (NCGA, S.B. 1009).
For owners
If you own a home on the north half of Topsail Island, these projects affect your property and your rental calendar. What to watch:
- Surf City owners: the first federal build is expected to start in early 2028 and run about 16 months, likely through at least one summer. Beach closure details haven’t been announced, so keep that in mind when you plan 2028 bookings (Coastal Review).
- North Topsail owners: the final EIS is expected around March 2027, followed by a public review period of at least 30 days. That is the next chance to comment on the groin plan (WECT).
- North end owners: under state coastal rules, sandbags are a temporary measure allowed only for imminently threatened structures, generally meaning the foundation, septic system or road right-of-way is less than 20 feet from the erosion scarp. The bags must sit landward of mean high water (NC Division of Coastal Management; 15A NCAC 07H .0308).
- Who pays: North Topsail’s 3% share of the occupancy tax on vacation rentals goes to its Shoreline Protection Fund, and Surf City’s beach fund draws on accommodations tax, property tax and paid parking. Rental income from your home helps fund the sand in front of it.
We follow these projects closely because they affect the homes we care for. If you have questions about how beach work might affect your home or your bookings, see our property management page or give our local team a call. If you’re weighing how to rent your home, read Airbnb vs. a property manager on Topsail Island.
For another look at how the island is changing, read about the nature preserve on Topsail’s south end.
Frequently asked questions
Is the beach open during nourishment?
Generally yes, outside the active work zone. In North Topsail Beach, truck-haul work runs on weekdays through a few designated accesses. During pipeline work, crews close only the section being worked and add crossings over the pipe.
When does beach nourishment happen on Topsail Island?
Usually between November 16 and April 30, to protect nesting sea turtles and shorebirds. Surf City’s first federal construction is the exception: it is expected to run year-round for about 16 months starting in early 2028.
Is North Topsail Beach part of the Army Corps project?
No. North Topsail Beach withdrew in 2021 over cost. The federal project now covers Surf City only, with a short transition into North Topsail Beach.
Has the North Topsail Beach terminal groin been approved?
No. The Corps’ environmental study is still in draft, with a final version expected around March 2027.
Is a terminal groin the same as a jetty?
No. A terminal groin is shorter, is pre-filled with sand and is designed to let sand pass. North Carolina law says outright that “a terminal groin is not a jetty.”